Marketing Campaign - Wearable Technology
Project Management Cost (Budget) (u07a1)
Introduction (Intent)
:
According to Bridges (2019), creating a project budget is a critical part of project planning as it
shows the total projected costs needed to complete the entire project over a defined period of time, for
each phase of the project.
The WBS phases that are estimated in this project are Project Management Phase
(Design/Initiation), Planning Phase, Technology Design Phase, The Marketing Design Phase, Training, and
the Project Close out phase. The Project Management Phase is expected to take 176 hours to complete,
and will cost an estimated $18,304.00. This phase accounts for 12.21 % of the total project budget to
complete the project charter, scope, cost breakdown, identify the project team, develop the project
schedule, and conduct the initial marketing research. The next phase is the planning phase, it is expected
to take approximately 136 hours and is estimated to cost $15,120 to develop the ERP upgrade plan,
marketing plan, training plan, risk plan, and hold the initial kickof call. The technology design phase is
expected to take 400 hours and cost approximately $46,800, it accounts for 31.21% percent of the
overall budget. This phase will consist of performing the ERP upgrade, Evaluating/Testing upgraded ERP,
internal testing of the ERP (Employee Use), change controls submitted, and then live implementation of
the new ERP. The Marketing Phase will take an estimated 392 hours to complete, and cost an estimated
$41,144.00 to complete, it accounts for 27.44% of the overall budget. This phase will consist of devloping
the brand strategy, pricing strategy, distribution strategy, Media Ad Design, internal marketing
presentation, change controls, and marketing plan implementation. Training is the next phase and it will
be 80 hours long for IT training and customer service training. The estimated budget for training is
$20,160.00. The project closeout phase is the final phase, it will take close an approximate 80 hours and
the estimated cost is $8,400.00.