Question 17 (3 points) Saved A Monte Carlo analysis (such as the one performed in Crystal Ball) usually provides which of the following for a project? Q The optimal assignment of resources to project activities Q The most cost-effective use of management's project supervision time O The critical path of the project A cumulative frequency distribution from which you can determine the probability of the project completing within a given time-frame