Week 7 SEE Assignment

.xlsx
Task BWCS Project Periods Value Added Roof Framing $1,200.00 $ 1,350.00 -$150.00 Framing Inspection $1,000.00 $ 770.00 $230.00 Frame 1st Floor Walls $1,600.00 $ 1,892.00 -$292.00 Frame 2nd Floor Decking $800.00 $ 1,014.00 -$214.00 Frame 2nd Floor Walls $1,200.00 $ 2,408.00 -$1,208.00 Lay 1st Floor Decking $800.00 $ 1,152.00 -$352.00 PM Period 4 $5,500.00 $ 6,192.00 -$692.00 PM Period 4 $5,500.00 $ 6,192.00 -$692.00 Roo f F raming Frami ng Insp ecti on Frame 1st Floor Wall s Frame 2nd Floor Decki ng Frame 2nd Fl oor Wal ls Lay 1s t Floor D ecking PM Period 4 PM Period 4 $0.00 $1,000.00 $2,000.00 $3,000.00 $4,000.00 $5,000.00 $6,000.00 $7,000.00 BWCS and Project Periods BWCS Project Periods Task