Template Lab Crashing solution with linear programming

.xlsx
Activity ID Slope ($) Max crash time A 0 0 B 100 1 0 C 60 1 D 40 1 0 E 0 0 F 30 2 G 20 1 H 60 2 1 0 I 200 1 0 Project duration Crashed activities Crash 17 - - 16 D 40 15 H 60 14 H 60 13 B 10 12 I 20
Direct Cost Normal Crash Time Cost Time Cost 3 150 3 150 4 200 3 300 3 250 2 310 4 200 3 240 2 250 2 250 3 200 1 260 2 250 1 270 4 300 2 420 2 200 1 400 h cost direct cost Indirect cost Total cost - 2000 1500 3500 40 2040 1450 3490 60 2100 1400 3500 60 2160 1350 3510 00 2260 1300 3560 00 2460 1250 3710 Paths/It ABF ABD ACD ACE
Path duration teration I1 I2 I3 I4 I5 FGI 14 14 14 14 13 DHI 17 16 15 14 13 DHI 16 15 14 13 13 EHI 14 14 13 12 12